- Heartland Park Expansion Project
The Heartland Park Expansion Project is set to transform 40 acres at the corner of White Oak Avenue and 109th Avenue into a vibrant community destination.
Plans for this exciting development include:
- An amphitheater with a stage and covered seating for large-scale events
- Multipurpose spaces and an open-air pavilion
- Indoor community rooms for year-round use
- A destination-style splash pad featuring slides, climbing structures, vertical water features, dry play zones, and a re-circulating water system
The building pad has been brought up to grade and roadway work is now underway. Foundation and utility installation will begin as soon as weather conditions cooperate. They are also anticipating the start of masonry work in May, once the rain finally gives us a break!
White Oak & 109th Roundabout
Engineers are completing the design of the roundabout. NIPSCO’s engineers are currently preparing plans to relocate their overhead and underground utilities to make room for the expanded roadway. Road construction is expected to begin this summer pending the status of utility relocations and right-of-way acquisitions.
- The Gates Pavilion & Permanent Restrooms
Permanent restroom facilities and a pavilion are coming to The Gates Park (10201 Park Pl, St. John, IN)! Grimmer Construction has begun work on the foundation for the permanent restrooms. Concrete footings have already been poured.. Work will continue throughout the spring, with an anticipated completion date this fall. While the project is underway, the park, including the playground and pickleball courts, will remain open with minimal disruption expected. We kindly ask all visitors to use caution and be mindful of construction activity while enjoying the park.
- Joliet Street Multi-Use Path Project
The Town Council awarded a contract to Dyer Construction as the lowest, most responsive and responsible bidder in the amount of $3,383,878.43 at their April 22nd meeting. Public Works Director, Gabe Hernandez, plans to host a resident meeting for those who live along Joliet Street in an effort to provide an opportunity for residents to learn about what to expect. A preconstruction meeting is scheduled for early May with construction to begin at the end of the month, weather dependent.
- Hedwig & Fehlberg Intersection Improvement
An engineering study is underway to determine the most cost-effective solution for correcting poor drainage at this intersection of Hedwig Dr. & Fehlberg Ct., and the standing water and ice around the curve on Hedwig Drive. Construction is expected to take place this summer pending the results of the study.
- Osage Drive Culvert Repair
The Osage Drive Culvert Repair Project consists of the lining of four large diameter storm sewer culvert pipes under Osage Drive and W 81st Court. The pipes will be internally lined to avoid needing to dig up the roads and disturb traffic. The lining will take place in this month and is expected to take less than one week to complete.
- Kilkenny Water Tank Altitude Valve
This project consists of the construction of a new building and installation of a new altitude valve at the Kilkenny Water Tower. The new valve will give the water department better control of pressure and circulation on the west side of Town. Construction began in mid-April and is scheduled to be completed by end of June.
- 2026 Town-Wide Paving
The Town is pleased to announce it has been awarded Community Crossings Matching Grant (CCMG) funding through the State of Indiana. This award allowed us to expand our 2026 paving program, adding nine additional roadways to this year’s project list. The Town Council awarded a contract to Milestone Contractors as the lowest, most responsive and responsible bidder in the amount of $1,762,198.15 at their April 22nd meeting. A preconstruction meeting was held on April 29th and construction is planned to begin the week of May 11th. Work is expected to be complete before the beginning of next school year, weather dependent. The Town appreciates the opportunity to leverage state funding to maximize local investment and continue delivering infrastructure improvements for residents.
