Town Projects

  • Heartland Park Expansion Project

    For those just catching up, the Heartland Park Expansion Project is set to transform 40 acres at the corner of White Oak Avenue and 109th Avenue into a vibrant community destination.

    Plans for this exciting development include:

    • An amphitheater with a stage and covered seating for large-scale events
    • Multipurpose spaces and an open-air pavilion
    • Indoor community rooms for year-round use
    • A destination-style splash pad featuring slides, climbing structures, vertical water features, dry play zones, and a re-circulating water system

    The construction entrance and laydown area have been installed. Mass earth grading is starting soon. In April, site utilities should begin as well as the foundation for the pavilion building.

    White Oak & 109th Roundabout

    Engineers are completing the design of the roundabout. NIPSCO’s engineers are currently preparing plans to relocate their overhead and underground utilities to make room for the expanded roadway. Road construction is expected to begin this summer pending the status of utility relocations and right-of-way acquisitions.

  • The Gates Pavilion & Permanent Restrooms

    Permanent restroom facilities and a pavilion are coming to The Gates Park (10201 Park Pl, St. John, IN)! Grimmer Construction is currently installing underground sanitary and water lines to support the new permanent restrooms. Work will continue throughout the spring, with an anticipated completion date this fall. While the project is underway, the park, including the playground and pickleball courts, will remain open with minimal disruption expected. We kindly ask all visitors to use caution and be mindful of construction activity while enjoying the park.

  • Joliet Street Multi-Use Path Project

    This Multi-Use Path will be constructed from 96th Pl to the Parrish Ave roundabout. The path will be between 8′ – 10′ wide. New ADA compliant curb ramps will be installed at each intersection with additional safety features. New drainage structures will be placed to accommodate the additional pavement. A Two-Way-Left-Turn Lane is being added to the project between Hart St and the Parrish Ave roundabout. This project is currently out to bid with bid opening to occur on April 10th. The Town Council anticipates awarding a contract at their April 22nd Town Council Meeting. Construction is anticipated to begin in May.

  • Hedwig & Fehlberg Intersection Improvement

    An engineering study is underway to determine the most cost-effective solution for correcting poor drainage at this intersection of Hedwig Dr. & Fehlberg Ct., and the standing water and ice around the curve on Hedwig Drive. Construction is expected to take place this summer pending the results of the study.

  • Osage Drive Culvert Repair

    The Osage Drive Culvert Repair Project consists of the lining of four large diameter storm sewer culvert pipes under Osage Drive and W 81st Court. The pipes will be internally lined to avoid needing to dig up the roads and disturb traffic. The lining will take place in May and is expected to take less than one week to complete.

  • Kilkenny Water Tank Altitude Valve

    This project consists of the construction of a new building and installation of a new altitude valve at the Kilkenny Water Tower. The new valve will give the water department better control of pressure and circulation on the west side of Town. Construction is expected to start the week of April 6th and be completed in July.

  • Well Houses 8 and 9

    Grimmer Construction has completed work on the well houses and the new connection to the Gates Water Treatment Plant. The project team continues to program the controls, flush the wells, and get everything ready for full operation. The wells will be pumping water to the treatment plant this March.