Town Projects

  • Heartland Park Expansion Project
    For those just catching up, the Heartland Park Expansion Project is set to transform 40 acres at the corner of White Oak Avenue and 109th Avenue into a vibrant community destination.
    Plans for this exciting development include:An amphitheater with a stage and covered seating for large-scale eventsMultipurpose spaces and an open-air pavilionIndoor community rooms for year-round useA destination-style splash pad featuring slides, climbing structures, vertical water features, dry play zones, and a re-circulating water system
    Core Construction is currently working through all of the submittals and waiting for the weather to warm up a bit. This project is planned to kick off in late February/early March.
    White Oak & 109th Roundabout
    Engineers are completing the design of the roundabout. NIPSCO’s engineers are currently preparing plans to relocate their overhead and underground utilities to make room for the expanded roadway. Road construction is expected to begin this Summer pending the status of utility relocations.
  • The Gates Pavilion & Permanent Restrooms

    Permanent restroom facilities are coming to The Gates Park (10201 Park Pl, St. John, IN)! The project was awarded to Grimmer Construction at the December 16, 2025 Park Board meeting. Grimmer will begin work on the project, beginning with utility connections and foundations through the Winter. Work will continue through the Spring with an anticipated completion date in June 2026. Minimal disruption to park usage is intended, including the playground and pickleball courts.

  • Joliet Street Multi-Use Path Project

    This Multi-Use Path will be constructed from 96th Pl. to the Parrish Ave. roundabout. The path will be between 8′ – 10′ wide. New ADA compliant curb ramps will be installed at each intersection with additional safety features. New drainage structures will be placed to accommodate the additional pavement. A Two-Way-Left-Turn Lane is being added to the project between Hart St and the Parrish Ave roundabout. This project will go out to bid in late February with bid opening to occur in late March.

  • Hedwig & Fehlberg Intersection Improvement

    An engineering study is underway to determine the most cost-effective solution for correcting poor drainage at this intersection of Hedwig Dr. & Fehlberg Ct., and the standing water and ice around the curve on Hedwig Drive. Depending on the final scope of work, construction may take place in the Summer or Fall of this year.

  • Osage Drive Culvert Repair

    The Osage Drive Culvert Repair Project consists of the lining of four large diameter storm sewer culvert pipes under Osage Drive and Osage Court. The pipes will be internally lined to avoid needing to dig up the roads and disturb traffic. The Town Council has awarded this project to Inliner Solutions, LLC in the amount of $230,000. Construction work is expected to take place in the spring or summer of this year.

  • Kilkenny Water Tank Altitude Valve

    The Waterworks Board has awarded this project to Hasse Construction Co. in the amount of $561,630. This project consists of the construction of a new building and installation of a new altitude valve at the Kilkenny Water Tower. The new valve will give the water department better control of pressure and circulation on the west side of Town. Construction is expected to start in early spring and be completed by July.

  • Well Houses 8 and 9

    Grimmer Construction has completed work on the well houses and the new connection to the Gates Water Treatment Plant. The project team continues to program the controls, flush the wells, and get everything ready for full operation. The wells will be pumping water to the treatment plant this March.