This Multi-Use Path will be constructed from 96th Pl. to the Parrish Ave. roundabout. The path will be between 8′ – 10′ wide. New ADA compliant curb ramps will be installed at each intersection with additional safety features. New drainage structures will be placed to accommodate the additional pavement. A Two-Way-Left-Turn Lane is being added to the project between Hart St and the Parrish Ave roundabout. This project will go out to bid in late February with bid opening to occur in late March.